Thursday, December 25, 2025

Aluform De-Shuttering – Methods

 

Aluform De-Shuttering – Methods, Safety & Quality Control (As per IS Standards)



Aluform (Aluminium Formwork System) is widely adopted in high-rise and mass housing because it ensures high speed, dimensional accuracy, superior finish, and monolithic strength.
However, unsafe or early de-shuttering can cause cracking, honeycombing, deformation, accidents, and structural failure.
Therefore, Indian Standards (IS) provide guidance on timing, safety, stability, inspection, and quality during formwork removal.


1️⃣ Relevant Indian Standards for Aluform De-Shuttering

Following standards should be considered during planning and execution:

  • IS 456:2000 – Plain & Reinforced Concrete Code

    • Clause 11.3 — Stripping time of formwork

    • Clause 13 — Concrete curing & protection

  • IS 3696 (Part 1 & 2) – Safety in Construction: Scaffolds & Working Platforms / Ladders

  • IS 4082 – Storage & Handling of Construction Material (Useful for stacking & handling Aluform)

  • IS 1200 (Part 5) – Formwork tolerances (good practice reference)

Always follow Project Specification + Consultant approval in addition to IS Code guidance.


2️⃣ De-Shuttering Time Requirement (As per IS 456:2000, Clause 11.3.1)   





De-shuttering depends on:
✔ Concrete Grade
✔ Temperature & Curing
✔ Member Type
✔ Structural Loading

Minimum Formwork Removal Time (IS 456 Table – Recommended Values)

Structural Member             Minimum Time (Normal Weather)
Vertical sides of walls, columns & beams          16 – 24 hours
Slab soffit (props left under)               3 days
Beam soffit (props left under)           7 days
Props for Slab up to 4.5 m span           7 days
Props for Slab over 4.5 m span           14 days
Props for Beams & Arches up to 6 m span           14 days
Props for Beams & Arches over 6 m span               21 days

Strength-Based Requirement

IS 456 also emphasizes that:

  • Concrete must gain minimum 70% of design strength before major de-shuttering.

  • Cube test report should be verified before stripping.


3️⃣ Aluform De-Shuttering Method (As per IS-Guided Good Practice)




A. Pre-De-Shuttering Checklist

Before removing formwork, ensure:

✔ Required stripping time completed (as per IS 456)
✔ Cube strength achieved (70% or above)
✔ Proper curing done (IS-456 clause 13 compliance)
✔ No cracks, deflection or deformation visible
✔ Temp supports stable
✔ Barricading & safety arrangements ready
✔ Engineer / QA-QC approval taken


B. Step-By-Step De-Shuttering Procedure

Step 1 – Safety Preparation (IS 3696 Compliance)

  • Isolate working zone

  • Display warning boards

  • Conduct toolbox talk

  • Provide lighting

  • Clear unwanted materials


Step 2 – Remove Non-Load Bearing Forms First

Remove in sequence:

  • External wall panels

  • Beam side shutters

  • Stair side shutters

No hammering allowed
Use only approved Aluform release tools.


Step 3 – Remove Slab Panels Carefully

  • Release with drop-head / pin system

  • Keep props as per IS 456 duration

  • Do not force panels


Step 4 – Controlled De-Propping

  • Remove props in phased manner

  • Follow IS 456 prop retention rules

  • Confirm upper floors are safe


Step 5 – Cleaning & Storage (As per IS 4082)

  • Clean using plastic / wooden scrapers

  • Do not bend, weld or hammer

  • Stack on flat stable surface

  • Segregate damaged panels


4️⃣ Safety Measures During Aluform De-Shuttering




A. Personal Protective Equipment (PPE)

Must as per IS 3696:

  • Helmet

  • Gloves

  • Safety Shoes

  • Goggles

  • Reflective Jacket

  • Harness (working at height)


B. Site Safety Practices

  • Close below working area

  • No movement under work zone

  • Use tag system

  • Avoid de-shuttering during rain/wind

  • Allow only trained workers


C. Equipment Safety

  • Use approved wrenches

  • Mechanical lifting if heavy

  • No gas cutting / welding on aluminium

  • Inspect tools daily


5️⃣ Quality Control During De-Shuttering

A. Post-Stripping Inspection (QA/QC)


Check for:

✔ Honeycombing
✔ Surface voids
✔ Cracks
✔ Dimensional accuracy
✔ Alignment / Plumb
✔ Level
✔ Surface finish


B. Dimensional & Finish Tolerances

(Refer IS 1200 Good Practice Guidance & Project Specs)

  • Verticality tolerance ±5 mm

  • Level tolerance ±5 mm

  • No structural cracks permitted

  • Honeycomb not acceptable

  • Repair immediately if found


C. Rectification Measures

  • Minor defects → polymer mortar repair

  • Honeycombing → remove loose concrete & repair with approved repair mortar

  • Severe defects → Consultant approval + NCR

  • Maintain repair records


6️⃣ Documentation Requirements

Maintain following records:

📌 Cube Test Report
📌 De-Shuttering Checklist
📌 Safety Permit / Toolbox Talk
📌 QA/QC Inspection Report
📌 NCR / Corrective Action Records

Good documentation improves transparency, audit compliance & safety reliability.


7️⃣ Common Mistakes to Avoid

❌ Removing form before IS time limits
❌ Ignoring cube strength
❌ Hammering aluminium panels
❌ Allowing people below working area
❌ No barricading
❌ Poor stacking damaging panels


Conclusion

Aluform de-shuttering is a critical structural & safety operation.
Following IS 456 stripping guidelines, IS 3696 safety norms, IS 4082 handling rules, and strong QA/QC discipline ensures:

✔ Structural safety
✔ High-quality finish
✔ Zero accidents
✔ Faster progress
✔ Reduced rework
✔ Long-term durability

Disciplined execution = Safe Structure + Quality Construction 👍

No comments:

Post a Comment

Surface Area of Concrete Ingredients – Strength, Workability & Durability”

  🏗️ “Surface Area of Concrete Ingredients – Strength, Workability & Durability” Concrete performance does not depend only on grade or ...