How to Calculate Wall Plaster – Cement & Sand
Plastering is an essential finishing work in construction that provides a smooth surface for walls and ceilings. To achieve a strong and durable plaster, correct calculation of cement and sand quantity is very important.
* Step 1: Understand Plastering Mix
The most commonly used plaster mix is Cement : Sand = 1:4 or 1:6 (by volume).
- 1:4 mix → For internal walls, bathrooms, wet areas
- 1:6 mix → For outer walls, normal plastering
* Step 2: Formula for Plaster Quantity
Plaster volume =Area of wall *Plaster thickness
- Area of Wall = Length × Height
- Thickness = Convert mm into meters (e.g., 12 mm = 0.012 m)
* Step 3: Add Wastage
Always add 30% extra for wastage and uneven surfaces.
# Example Calculation
Given:
- Wall size = 10 m (length) × 3 m (height) = 30 m²
- Plaster thickness = 12 mm = 0.012 m
- Mix ratio = 1:4 (Cement:Sand)
*. Step 1: Wet Volume of Plaster
Wet Volume= 30 * 0.012 = 0.36 m3
Add 30% wastage:
0.36 * 1.30 =0.468 m³
* Step 2: Dry Volume
Since dry volume = Wet volume × 1.33
0.468 * 1.33 = 0.622 m³
* Step 3: Cement & Sand Calculation
Mix = 1:4 → Total = 1 + 4 = 5 parts
- Cement = (1/5) × 0.622 = 0.124 m³
- Sand = (4/5) × 0.622 = 0.498 m³
* Step 4: Convert Cement into Bags
1 m³ cement = 1440 kg
1 bag cement = 50 kg → 0.0347 m³
0.124 ÷ 0.0347 = 3.6 bags
👉 So, for 30 m² wall (12 mm thick, 1:4 mix):
- Cement = 4 bags (approx.)
- Sand = 0.50 m³ (before bulkage)
# Bulkage of Sand – Importance in Construction
* What is Bulkage of Sand?
When sand contains moisture, a thin film of water forms around each particle. This traps air between particles and increases the apparent volume of sand.
👉 Example: 1 m³ of dry sand may look like 1.2 m³ moist sand (20% extra volume).
This phenomenon is called Bulkage of Sand.
* Why is Bulkage Important?
- Mix Proportion Error – If bulkage is ignored, the actual sand going into mortar or plaster will be less than required.
- Weak Plaster/Concrete – Reduced sand → higher cement content → cracks and shrinkage.
- Cost Effect – Wrong proportions increase material usage and cost.
- Workability Issue – Bulked sand changes the consistency of mortar/concrete.
* Bulkage Correction Formula
Corrected sand Volume =Calculated sand Volume
Example:
- Required Sand = 0.50 m³
- Bulkage = 20%
0.50×1.20 = 0.60 m³
👉 So, 0.60 m³ moist sand is needed to get 0.50 m³ dry sand equivalent.
* Practical Site Note
- Bulkage of sand generally varies between 15% – 30% depending on moisture.
- A field test can be done:
- Fill a container with moist sand.
- Pour water to remove air gaps.
- The sand level drops – the difference shows bulkage %.
* Key Takeaway
Bulkage of sand is a critical factor in plastering and concrete works.
Always adjust sand quantity by adding 20–30% (depending on site moisture) to maintain correct mix proportions and avoid strength problems.
* Final Answer
To plaster a 10 m × 3 m wall (12 mm thick, 1:4 mix):
- Cement → 4 Bags
- Sand → 0.60 m³ (after bulkage adjustment)
* Key Notes
- For ceiling plaster, add extra 10% due to wastage.
- Always check sand quality (silt content < 8%).
- Use potable water for mixing.
- Adjust bulkage based on site moisture test.
No comments:
Post a Comment