building construction sequence of activities
1. Pre-Construction Stage
1.1 Planning & Design
- Requirement gathering – Owner, architect, and engineers discuss needs, budget, size, and function of the building.
- Site survey & soil investigation – Topographical survey, borehole tests, and geotechnical reports to understand ground conditions.
- Architectural drawings – Floor plans, elevations, sections prepared.
- Structural design – Foundation, beams, slabs, columns designed as per load requirements and building codes (e.g., IS 456, IS 800).
- Service designs – Electrical, plumbing, HVAC, fire safety systems.
- Approvals – From local municipal corporation, environment department, etc.
2. Site Preparation
2.1 Mobilization
- Setting up site office, storage, labour camp, and arranging utilities (water, electricity).
- Safety arrangements – fencing, signboards, PPE.
2.2 Clearing & Grading
- Clearing vegetation, old structures, debris.
- Site leveling and marking boundaries.
3. Foundation Works
3.1 Setting Out
- Marking the building layout on the ground using survey equipment.
3.2 Excavation
- Trench or pit excavation for foundation as per design.
- Dewatering if groundwater is encountered.
3.3 Foundation Construction
- PCC (Plain Cement Concrete) bed.
- Foundation type:
- Shallow (isolated footing, strip footing, raft)
- Deep (pile foundation, well foundation)
- Reinforcement fixing, formwork, and concreting.
3.4 Plinth Level
- Plinth beam casting.
- Backfilling & compaction inside plinth.
- Damp Proof Course (DPC) application.
4. Superstructure Works
4.1 Column Construction
- Reinforcement tying, shuttering, concreting for columns.
4.2 Beam & Slab Works
- Beam reinforcement & shuttering.
- Slab reinforcement, electrical conduit laying, concreting.
4.3 Masonry Work
- Brick/block wall construction.
- Lintel beams above openings.
5. Roofing
- Casting of top slab or installation of trusses (if steel/timber roof).
- Waterproofing treatments.
6. Finishing Works
6.1 Internal & External Plastering
- Cement plaster on walls and ceilings.
6.2 Flooring
- Sub-base concrete, floor finish (tiles, stone, etc.).
6.3 Joinery
- Fixing doors, windows, frames.
6.4 Painting
- Putty, primer, paint coats.
7. Services Installation
- Electrical – Wiring, switchboards, fixtures.
- Plumbing – Water supply lines, drainage, sanitary fittings.
- HVAC – Ducting, AC units, ventilation systems.
- Fire Safety – Sprinklers, alarms.
8. External Development
- Compound wall, gates.
- Landscaping.
- Paving, approach roads.
9. Testing & Commissioning
- Checking electrical, plumbing, and HVAC systems.
- Testing concrete strength, plumbing leakage, waterproofing, etc.
10. Handover & Occupancy
- Final cleaning of site.
- Documentation – drawings, manuals, warranty papers.
- Formal handover to owner.
📌 Quick Flow Chart of Building Construction Sequence:
- Planning & Design
- Site Preparation
- Foundation Work
- Plinth Level
- Superstructure (Columns, Beams, Slabs)
- Masonry Walls
- Roofing
- Finishing Works
- Services Installation
- External Development
- Testing & Handover